Testimonials

“Steve, Alison,

Just a brief note to say it’s been a pleasure working with you guys on the DPD, Network 46 Project over the course of the last 12 months.

I visited the site earlier in the week and it looked excellent.

Hopefully there will be plenty of other opportunities for UMC and Quantum to work together again in the future.

Many Thanks again,

Matthew Salanyk

Director”



Geopost Network 46 - Matthew Salanyk, UMC Architects

Projects - National Grid, Erdington
National Grid, Erdington

Download Project Specification Sheet PDF
Project:
National Grid, Erdington
Location:
Erdington, Birmingham
Value:
£740,000
Client:
National Grid
Contract:
JCT 2005 Without Quantities
Duration:
25 Weeks
Architect:
Richards Partington Architects
Structural Engineer:
Cundall
 
Download Project Specification Sheet PDF

Works undertaken within National Grid’s existing Birmingham facility, immediately adjacent to the River Tame.

The heavily contaminated site was further constrained by two live 900mm diameter gas mains traversing the site close to the works, along with a plethora of other unknown buried
services crossing the site.

Vibration monitoring of driven piles was undertaken as part of the safety process to avoid fracture of the gas mains.

All the works were carried out within close proximity of the client’s own activities without disruption.