“The new headquarters manufacturing facility for Atlas Copco was a complicated project involving a high level of fit-out in both the offices and the manufacturing area.  Quantum did a fantastic job delivering this scheme and both Mucklow and the occupier are delighted with the outcome.

Mark Vernon

Investment Director”



A & J Mucklow Group Plc

Projects - Millfields Road, Ettingshall
Millfields Road, Ettingshall

Download Project Specification Sheet PDF
Project:
Millfields Road, Ettingshall
Location:
Millfields Road, Ettingshall, Wolverhampton
Value:
£1,529,997
Client:
Utopia Group Ltd
Contract:
Amended JCT 1998 WCD
Duration:
36 Weeks
Architect:
P D Architects
Structural Engineer:
Nolan Associates
 
Download Project Specification Sheet PDF

Quantum Construction Limited acted in the dual role of Project Manager and Main Contractor within the framework of a Design and Build Contract.

The project comprised the construction of new warehouse accommodation 2,006m2 (21,600sq.ft.), including 886m2 (9,536sq.ft) of mezzanine, new two storey office accommodation 321m2 (3,455sq.ft.) and refurbishment to existing warehouse approximately 1,152m2 (12,400sq.ft).

Warehouse design incorporated a concrete mezzanine serviced by two goods lifts, vehicle docking facilities incorporating inflatable shelters, levelling plates and traffic
management control system.

Site works included demolition of existing building, along with removal of underground structures of air raid shelter and redundant fuel tanks from earlier petrol station.

Grouting of underlying mine workings and vibropiling of top surfaces were undertaken to improve existing ground conditions.