Testimonials

“Lands’ End is a well known clothing retailer which operates from their 240,000 square foot, state of the art distribution centre in Rutland. The company has been in the industry since 1963 and has grown from their origins in Wisconsin, USA to supply most of Europe through their online network.

Quantum Construction worked on the multi million pound extension to their European distribution centre, delivering the project ahead of schedule whilst meeting the detailed environmental challenges imposed by the client.

Adam Osbourne, Facilities Manager for the Lands’ End Company says, “Quantum Construction has provided our company with a successful and efficient service on the extension of our facility. They are always ready and willing to help with any enquiry and we are extremely pleased with the service our company has received.”



LANDS' END

Projects - Charter House Holdings Plc
Charter House Holdings Plc

Download Project Specification Sheet PDF
Project:
Charter House Holdings Plc
Location:
Trent Lane, Castle Donnington, DE74 2PY
Value:
£730k
Client:
Charter House Holdings Plc
Contract:
JCT Intermediate Building Contract With Contractors Design 2011
Duration:
30 weeks
Architect:
JT Design Partnership
Structural Engineer:
100 Nine Design Limited
 
Download Project Specification Sheet PDF

The main works consist of a 22,090ft2 (2,052m2) extension to an existing distribution warehouse, including associated external works, alterations to existing underground drainage system, new parking and landscaping.

 

The new steel portal, complete with profiled metal cladding, was specified and constructed to precisely match the existing building.

 

Essential to success of the project was the maintenance of access, for the client’s distribution operations, across a small shared access yard.

 

The degree of difficulty in managing the operation was high due to the new construction being undertaken along two sides of the existing yard with the client’s existing building on the third.

 

Careful planning of the works, including undertaking specific tasks to suit the particular periods of high intensity use of the existing facility by the client, was successfully translated into the programme for the works.