Projects - Auchentullich Farmhouse
Auchentullich Farmhouse

Download Project Specification Sheet PDF
Project:
Auchentullich Farmhouse
Location:
The Carrick, Loch Lomond
Value:
£1,450,000
Client:
DeVere Group Plc
Contract:
Scottish JCT 1998 WCD
Duration:
28 Weeks
Architect:
G D Lodge Architects
Structural Engineer:
W A Fairhurst & Partners
 
Download Project Specification Sheet PDF

The project required construction of replica farmhouse and courtyard, finished in local materials, to replace earlier structures demolished to make way for a new golf course. Only the highest level of quality was acceptable to the De Vere Group, due to the project being a key part of their flagship development. Client expectations were achieved and acknowledged by all parties.

Construction of the buildings comprised of timber framed structural members with local stone external cladding. The stonework was completed with dressed stone mullions and cills to window and doorways. Reclaimed Scottish slate tiling was fixed to traditional sarking boarding to the roofs.
The high specification for the internal finishings included sound and vision systems, throughout each building, linked into the site wide media infrastructure system.

Included within the contract was installation of furniture and fittings, presenting the buildings ready for immediate occupancy.